Kriel Power Station Boilers Apertures and Bottom Ash Hoppers Refractory Supply and Services for a period of Five Years on an As-and-When required basisClosed
Summary
AI-generated from the tender documents.
Overview
Procurement of Kriel Power Station Boilers Apertures and Bottom Ash Hoppers Refractory Supply and Services for five years on an as-and-when required basis. Bid is open to refractory materials and services providers capable of high-temperature boiler refractory supply, installation, repair and QA. Key sourcing context and evaluation approach are outlined in the attached strategy and scope documents (Scope.pdf; Tender Technical Evaluation Strategy: Kriel PS Boilers Apertures and Bottom Ash Hoppers Refractory Supply and Services for a period of five years on an As-and-When required basis. Rev 2.pdf).
Requirements
- Supply/repair/instate refractory for boiler apertures and ash hoppers; materials up to 1400–1600 °C. (Scope.pdf)
- ISO 9001:2015 QMS certification plus a signed QMS policy.
- Detailed Method Statement covering supply to specification, QA verification, on/offsite storage, safe handling, and on-site/ manufacturer liaison.
- Quality Control Plan (QCPs): three historically signed plans preferred; include stakeholders’ sign-off.
- Evidence of personnel experience: site supervisor, project manager (minimum years), and at least eight operators.
- MSDS documentation for refractory materials with specified properties.
- Three material specification sheets with verifiable purchase orders; indicate lead contractor in JV if applicable.
- Approved project schedule showing tasks, resources, and timelines.
- Installation/inspection records from the lead contractor.
- Compliance with QM58 Supplier Quality Management Specification (referenced).
(From Tender Technical Evaluation Strategy: Kriel PS Boilers Apertures and Bottom Ash Hoppers Refractory Supply and Services for a period of five years on an As-and-When required basis. Rev 2.pdf; Scope.pdf)
How to Apply
- Submission deadline: 26 June 2026 at 10:00; briefing: 10 June 2026 at 10:00; site briefing at Cnr Orgies Bathal road, Kriel 2271.
- Submission method: via Eskom E-Tendering portal.
- Documents to submit (illustrative): signed commitment letter; ISO 9001 certificate and QMS policy; method statement; QCPs; MSDS and material specs; three materials specs with POs; evidence of key personnel; installation/inspection records; approved project schedule; proof of workshop ownership/lease if required.
- Pre-qualifications: ISO 9001 QMS; QM58 references; applicable to Scope of Work (Scope.pdf; NEC3 framework in NEC.pdf).
- Tender evaluation: minimum technical threshold of 70%; detailed scoring via the Tender Technical Evaluation Strategy (Rev 2.pdf).
Documents referenced: Scope.pdf, Tender Technical Evaluation Strategy: Kriel PS Boilers Apertures and Bottom Ash Hoppers Refractory Supply and Services for a period of five years on an As-and-When required basis. Rev 2.pdf, NEC.pdf.
Kriel Power Station Boilers Apertures and Bottom Ash Hoppers Refractory Supply and Services for a period of Five Years on an As-and-When required basis Kriel Power Station Boilers Apertures and Bottom Ash Hoppers Refractory Supply and Services for a period of Five Years on an As-and-When required basis Documents available from: 03 June 2026 Site Meeting: Yes Municipality: Nkangala District Municipality
- Tender documents (27 files).zip
Want tenders like this one in your inbox?
Create a free account to search every open tender and download the documents.